Home Electrification & Title 24 Reach Codes in Santa Clara & San Mateo Counties

A remodel does not automatically require every appliance to become electric, but additions and alterations must meet the energy requirements applicable to their scope. In Santa Clara and San Mateo counties, a sound electrification plan coordinates the 2025 California Energy Code, current local requirements, equipment design, and the capacity of your electrical service.

Whole-Home Remodels

Published by Heartwood Residential · Updated

Key takeaways

  • The 2025 Energy Code took effect January 1, 2026; additions and alterations have scope-specific compliance requirements.
  • Local reach codes vary and change, so confirm the current ordinance and its application to your project rather than assuming a regional rule.
  • Heat pumps, induction, EV charging, and future solar or batteries should be evaluated as one coordinated electrical load plan.
  • A panel replacement, utility service upgrade, and smart load management are different interventions; calculations determine which are appropriate.
  • Confirm your electric utility early: Palo Alto uses CPAU, while many surrounding communities receive electric delivery through PG&E.

What Title 24 requires for additions and alterations

Title 24 Part 6 is California’s Energy Code, and its 2025 edition took effect January 1, 2026. Title 24 is the broader California Building Standards Code; CALGreen is Part 11, not another name for the Energy Code. Confirm the code edition governing the permit application and the requirements attached to the actual work.

An addition creates new conditioned space, while an alteration changes existing components or systems; a project may include both. Requirements can address insulation, fenestration U-factor and solar heat gain coefficient, duct sealing, lighting controls, and heating or water-heating equipment. Replacing a system and leaving it untouched are different compliance situations. Do not transfer new-home requirements wholesale onto a limited kitchen remodel.

The 2025 code strongly favors heat pumps in new construction, but that does not establish a universal all-electric mandate for every existing-home renovation. An energy consultant should identify the applicable prescriptive route or performance approach using CBECC-Res where appropriate. Certain measures require Home Energy Rating System, or HERS, field verification; allow for documentation and testing in the construction sequence.

Reach codes and the changing local regulatory landscape

Reach codes are local requirements that exceed the statewide baseline, and their applicability must be confirmed for each project. A rule may distinguish new buildings from additions, major alterations, or equipment replacements. Ask which requirements apply to the proposed scope and permit timing instead of relying on a summary written for a different kind of project.

Many Silicon Valley cities adopted all-electric new-construction policies around 2019–2022. Following the 2023 Ninth Circuit decision in California Restaurant Association v. City of Berkeley, many jurisdictions paused, amended, or replaced natural-gas prohibitions with other approaches, including energy-performance or electric-readiness provisions. The decision should not be read as eliminating state energy requirements or making every local electrification measure identical.

Requirements vary and are actively changing; Heartwood Residential confirms the current ordinance per project. This article does not state that any particular city currently bans gas or requires a specific replacement appliance. Before design decisions become fixed, obtain project-specific confirmation of applicable energy provisions, electrical readiness, and any separate local requirements.

Electric-readiness starts with loads, circuits, and space

Electric-ready design preserves practical paths for future equipment even when the remodel does not electrify everything immediately. It can include reserved panel capacity, dedicated circuits, conduit routes, equipment locations, and space for future heat pump, induction, or EV connections. The required provisions depend on the applicable code and scope; voluntary readiness can extend beyond that minimum.

Begin with an electrical load calculation covering existing loads and plausible future equipment. A new panel does not necessarily increase the utility service capacity, and a service upgrade is not automatically necessary whenever an appliance becomes electric. The electrician and design team should distinguish panel condition, breaker space, service rating, and calculated demand rather than treating them as interchangeable.

Load management can coordinate compatible loads to stay within a designed limit; some smart panels provide related monitoring or control functions. Neither label guarantees code acceptance, utility approval, or compatibility with every appliance. Compare a documented managed-load strategy with a service upgrade, and reserve accessible pathways while walls are open so future work does not undo finished interiors.

The equipment stack: design interacting systems together

Electrification works best when heating, hot water, cooking, transportation, and future generation are designed as interacting systems. Size equipment from actual needs rather than simply matching the old gas appliance rating. Improved insulation or windows may change heating and cooling loads, so finalize envelope assumptions before selecting HVAC capacity.

A heat pump HVAC system needs a room-by-room comfort strategy, suitable ductwork or indoor units, condensate routing, and an outdoor location that addresses noise and service access. A heat pump water heater needs appropriate space, air access, condensate handling, and a hot-water delivery plan. Confirm manufacturer installation requirements rather than assuming either appliance can occupy the old equipment location unchanged.

Induction cooking requires the correct circuit and appliance fit; maintain effective kitchen ventilation rather than treating electric cooking as ventilation-free. Include EV charging in the load calculation and consider solar and battery pathways, roof conditions, inverter locations, and backup priorities. Solar generation does not by itself resolve service capacity, and backup operation requires a deliberately designed system with appropriate controls and approvals.

Know your utility: PG&E, CPAU, SVCE, and PCE

The organization selling your electricity may differ from the utility responsible for service equipment and interconnection. In many surrounding communities, PG&E handles electric delivery and service upgrades. Palo Alto operates its own municipal utility, City of Palo Alto Utilities, or CPAU, so electric service coordination there goes through CPAU rather than PG&E.

Silicon Valley Clean Energy, or SVCE, and Peninsula Clean Energy, or PCE, are community choice energy providers serving much of Santa Clara and San Mateo counties. In participating PG&E service areas, they generally supply the generation portion of electricity while PG&E continues delivery. Confirm the provider on your bill and the property’s service arrangement rather than inferring it solely from the county.

SVCE and PCE have offered electrification programs, but availability and eligibility can change. Verify current terms before selecting equipment or starting work; do not assume support is guaranteed. Separately, ask the delivery utility about service capacity, meter location, equipment clearances, interconnection, and lead times early enough that utility coordination does not become a surprise after interior work is complete.

Sequence electrification within the remodel

The most effective sequence resolves compliance and service capacity before demolition, then installs concealed infrastructure before finishes. Start with household goals, existing equipment condition, the planned addition or alteration, and an inventory of future loads. Have the design team align the energy documentation, electrical calculation, mechanical design, and proposed permit scope.

Next, confirm utility requirements and any local provisions before committing to equipment locations. Resolve outdoor-unit placement, water-heater space, panel clearances, and circuit pathways alongside the architectural plan. If electrification will occur in stages, identify which circuits and routes should be installed now and how interim heating, cooking, and hot water will remain available during construction.

During construction, coordinate rough electrical and mechanical work, inspections, insulation, testing, and equipment commissioning. Closeout should include operating instructions, required compliance documents, and a clear explanation of load controls or backup circuits. A staged plan is useful only when the later phase remains technically practical, so document reserved capacity and routes instead of relying on memory.

Homeowner checklist before equipment selection

A complete homeowner brief states both the immediate remodel scope and the household’s likely future electrical needs. Bring utility bills, available plans, equipment information, and photographs of the panel and service area to the planning conversation. Treat photographs as starting information, not a substitute for professional inspection or a load calculation.

  • Confirm the permit’s code edition, applicable addition or alteration requirements, current local reach provisions, and required energy documentation or field verification.
  • Identify the electric delivery utility and generation provider; ask who handles service upgrades, interconnection, and any currently available programs.
  • List existing and future HVAC, water heating, cooking, laundry, EV charging, solar, and battery goals for the electrical load calculation.
  • Compare service upgrades with compliant load management; verify equipment compatibility, clearances, circuit sizing, and space for future work.
  • Coordinate equipment placement, noise, condensate, ventilation, roof work, temporary services, inspections, and commissioning before finishes are specified.
  • Keep approved plans, compliance records, equipment manuals, and a labeled circuit schedule so later electrification phases build on verified information.

This guide is general information, not legal or code advice. Rules change; Heartwood confirms current requirements with the jurisdiction during every project's feasibility phase.

Questions

Frequently asked

Does the 2025 Energy Code require my entire existing home to be electric?

Not automatically. Additions and alterations must comply with requirements applicable to their scope, and replacing equipment can bring different obligations than leaving it unchanged. Local provisions may add requirements, but those must be verified for the project. Ask the energy consultant and permitting team to identify the specific compliance obligations before assuming either that everything must change or that existing systems are exempt.

Can a smart panel avoid an electrical service upgrade?

In some projects, an approved load-management design may allow selected loads to operate within existing service limits. It is not a universal substitute for additional capacity. The answer depends on the load calculation, equipment compatibility, electrical code requirements, utility conditions, and the household’s operating needs. Have the electrician distinguish monitoring features from actual load control and document how the proposed system limits demand.

Should I choose the heat pump before improving insulation?

Coordinate the two decisions rather than sizing the system in isolation. Planned insulation, air sealing, and window changes affect heating and cooling loads and can influence equipment selection. Establish the intended building envelope, then have the mechanical designer calculate loads and plan distribution. Also confirm outdoor-unit location, electrical supply, condensate routes, and installation access before architectural finishes make those decisions harder to change.

Do SVCE or PCE arrange the electrical service upgrade?

Generally, service upgrades in their participating PG&E delivery areas are coordinated with PG&E, not the community choice generation provider. SVCE or PCE may offer relevant programs, subject to current eligibility and terms. Palo Alto is different because CPAU operates the municipal utility. Check the property’s bill and confirm the responsible utility before planning meter changes, service capacity, or interconnection work.